Kat13, energy-efficient renovation – project by Studio giving form, architects in Berlin

Kat13, energy-efficient renovation

A detached house in Berlin-Nikolassee is comprehensively renovated, upgraded for energy efficiency and extended.

Location
Berlin-Nikolassee
Brief
Renovation with extension, KfW 55
Work stages
1–8
Status
Completion spring 2027

The detached house on Katteweg is being converted into two apartments to the KfW 55 standard, with an extension towards the garden and a fully underpinned basement.

Planning and execution by Studio giving form in work stages 1 to 8, with completion planned for spring 2027. The building receives 20 cm of insulation all round and new, generously glazed window openings with black aluminium windows by Schüco.

The extension

A new extension is added on the garden side. In the upper apartment it houses the dining area, in the lower apartment the living room. Large, newly cut window openings and continuous glazing open both rooms to the garden. All windows have black aluminium frames by Schüco.

Two apartments, one new staircase

Two units are created, an upper and a lower apartment, with new internal access: a new staircase links both levels inside the building rather than outside as before. The old bathroom and a small room make way for the new staircase, and the layout is reorganised accordingly.

The kitchen of the upper apartment sits in the former dining room and gets a kitchen island. The lower apartment has its own, fully equipped kitchen. In the upper apartment, living and kitchen form one open area oriented towards the new, generously glazed windows with views of the garden. The existing fireplace is brought back into use. In the lower apartment the living room is in the extension.

The dining area of the upper apartment is in the extension, the brightest room of the conversion, with large-scale glazing to the garden. The kitchen, by contrast, lies inside the house, in the former dining room.

Basement and building services

The entire basement is underpinned by about 1.50 m, with a new reinforced concrete floor slab and new waterproofing. This creates additional space and new possibilities below ground. The building services comprise a central ventilation system with a 50 m ground collector, a heat pump and PV panels on the roof, forming the basis for the KfW 55 standard.

Credits

Planning and execution: Studio giving form. Energy consulting: Mr Freitag. Structural engineering: Bauatelier, Mr Ile.