Anyone who builds in Germany soon hears words nobody explains: HOAI, LP 5, BGF, GRZ. Here are the most important terms and abbreviations, briefly and in a way that needs no prior knowledge.

Throughout our website these terms have a dotted underline. A click takes you straight to the explanation. Missing a term? Write to us and we will add it.

Fees and process

HOAI (German fee regulation for architects and engineers) HOAI
The HOAI sets out how architectural and engineering services are described and remunerated in Germany. It divides the work into nine work stages and contains fee tables. Since 2021 these tables are a guide; the fee is freely agreed between client and architect.
Leistungsphasen (work stages) LP
The nine steps of an architect’s work under the HOAI: 1 establishing the basis, 2 preliminary design, 3 final design, 4 permit planning, 5 detailed design, 6 preparing the tender, 7 assisting with the award, 8 site supervision, 9 post-completion support. You can commission all stages or individual ones.
Grundlagenermittlung (establishing the basis) LP 1
The first step: what is to be built, for whom, where and on what budget? The architect clarifies the brief, the plot, planning law and constraints and advises on how to proceed.
Vorplanung (preliminary design) LP 2
First sketches and options at small scale. This is where the concept is chosen, accompanied by a first cost estimate.
Entwurfsplanung (final design) LP 3
The chosen concept becomes a fully worked design: floor plans, sections, elevations, materials and a cost calculation. After this it is settled what the building looks like and how it works.
Genehmigungsplanung (permit planning) LP 4
The design is turned into the documents for the planning application: drawings, building description, calculations and verifications. The architect submits the application and accompanies the process.
Ausführungsplanung (detailed design) LP 5
The drawings that are actually built from: at scales from 1:50 to 1:1, with all dimensions, materials and details. The more precise the detailed design, the fewer queries and variations on site.
Bauüberwachung (site supervision) LP 8
The architect checks on site that work follows the drawings, the contract and recognised technical standards. They coordinate the contractors, check invoices, keep the schedule and organise final acceptance.
Objektbetreuung (post-completion support) LP 9
After completion: the architect accompanies the warranty period, inspects the building before the deadlines expire and makes sure contractors remedy defects.
Anrechenbare Kosten (eligible costs)
The part of the construction costs on which the architect’s fee under the HOAI is based. It mainly comprises the costs of the building structure and, in part, of the technical systems.
Honorarzone (fee zone)
The HOAI classifies building tasks by difficulty into five fee zones, from I (very simple) to V (very demanding). A house usually falls into zone III or IV.
Künstlerische Oberleitung (artistic supervision)
If another firm takes over detailed design or site supervision, the design architect uses artistic supervision to make sure the design idea is preserved.
Leitdetails (key details)
Selected, precisely drawn key points of a building, such as window junctions, parapets or plinths. They set the design quality that all other details follow.

Planning law and permits

Bauantrag (planning application)
The application for a building permit at the building authority. It consists of drawings, a building description, calculations and verifications and must be signed by a person authorised to submit it, usually an architect.
Baugenehmigung (building permit)
The authority’s written permission to build a project as applied for. Work may not start without it. It is valid for a limited time and may include conditions.
Bauvoranfrage (preliminary planning enquiry)
A preliminary enquiry settles individual questions bindingly in advance, such as whether and how large you may build. The authority’s answer is called a Bauvorbescheid and binds it for a limited period. This gives certainty before a purchase or costly planning.
Bebauungsplan (local development plan) B-Plan
A municipality’s development plan sets out bindingly for an area what may be built: type of use, size, height, building type and buildable areas.
Section 34 BauGB (building without a development plan) § 34 BauGB
Where there is no development plan, section 34 of the Federal Building Code applies within built-up areas: a project is permissible if it fits into its surroundings in type, scale, building form and footprint. In Berlin this applies to a great many plots.
Baugesetzbuch (Federal Building Code) BauGB
The federal law for planning. It governs where and what may be built in principle, for example through development plans.
Bauordnung (state building code) BauO Bln
Each federal state has its own building code, in Berlin the BauO Bln. It governs how buildings must be built: spacing, fire safety, escape routes, accessibility and the approval procedure.
Grundflächenzahl (site coverage ratio) GRZ
The GRZ states what share of the plot may be built over. A GRZ of 0.3 means: on a 1,000 m² plot, 300 m² of footprint may be built.
Geschossflächenzahl (floor area ratio) GFZ
The GFZ states how much floor area may be created in relation to the plot area. With a GFZ of 0.8, a 1,000 m² plot allows 800 m² of floor area across all full storeys.
Abstandsflächen (spacing areas)
Areas in front of external walls that must stay free of buildings to secure light, air and fire safety. Their depth depends on wall height; in Berlin it is generally 0.4 of the wall height, at least 3 metres.
Baufenster (buildable area)
The Baufenster is the part of the plot where building is allowed. It is defined by Baugrenzen (which may not be exceeded) and Baulinien (on which you must build).
Vollgeschoss (full storey)
A storey that reaches certain heights under the state building code and therefore counts towards the permitted number of storeys. Basements and converted attics may not count, depending on their height.
Nutzungsänderung (change of use)
If a room or building is used differently from what was approved, such as a shop becoming a practice or restaurant, a permit is usually needed even without building work. Fire safety, escape routes, parking and sound insulation are among the things checked.
Bauvorlageberechtigung (authorisation to submit applications)
Only someone with this authorisation may sign and submit a planning application. These are mainly architects registered with a chamber of architects.
Gebäudeklasse (building class) GK
The building code divides buildings by height and size into classes 1 to 5. The higher the class, the stricter the requirements for fire safety and escape routes.

Areas and key figures

Brutto-Grundfläche (gross floor area) BGF
The sum of the floor areas of all storeys of a building, measured to the outer edges and therefore including the walls (DIN 277). The BGF is the key figure for early cost estimates and for comparing buildings.
Netto-Raumfläche (net room area) NRF
The usable area between the walls, excluding construction. It consists of usable area, plant area and circulation area. It was formerly called Netto-Grundfläche (NGF).
Nutzungsfläche (usable area) NUF
The part of the net room area that serves the building’s actual purpose: living, offices, sales, storage. Corridors, stairs and plant rooms are not included.
Wohnfläche (living area) WoFl
The area of a dwelling under the German Living Space Ordinance. Areas under sloping roofs count only half or not at all depending on ceiling height; balconies and terraces usually count a quarter.
Brutto-Rauminhalt (gross volume) BRI
The volume of a building, measured to its outer surfaces, from foundation to roof. The BRI is used for cost benchmarks and for some fees.

Costs and tendering

DIN 276 (building costs) DIN 276
The standard for structuring building costs. It sorts all costs into cost groups and describes the stages of costing: estimate at preliminary design, calculation at final design, cost plan at award and final account at the end.
Kostengruppen (cost groups) KG
The breakdown of building costs under DIN 276: 100 site, 200 preparatory work, 300 building structure, 400 technical systems, 500 external works, 600 fittings, 700 ancillary costs (including consultants’ fees), 800 financing. “Pure construction costs” usually means groups 300 and 400.
Leistungsverzeichnis (bill of quantities) LV
The exact description of all work in a trade, item by item with quantities. Contractors enter their prices, which makes quotes comparable.
Ausschreibung und Vergabe (tendering and award)
In tendering, contractors are asked for quotes based on the bills of quantities. The architect compares them in a price comparison and recommends which firm should get the job. The client decides.
VOB (German construction contract procedures) VOB
A set of rules for construction contracts. Part B contains balanced contract terms between client and contractor, Part C the technical rules of the individual trades. VOB/B applies only if agreed.
Nachtrag (variation)
A subsequent claim by a contractor for work that was not, or differently, included in the contract. The architect checks whether the variation is justified and the price reasonable.
Abnahme (final acceptance)
With acceptance the client confirms that work has essentially been carried out as contracted. Defects are recorded in a report. The warranty period starts from this point.
Gewährleistung (warranty for defects)
The period after acceptance in which a contractor must remedy defects at its own cost: five years for buildings under the German Civil Code, four years where VOB/B is agreed.
Generalunternehmer (general contractor) GU
A general contractor builds the whole building as a single party and hires further firms itself. With separate trade contracts the client contracts with each trade. That is often cheaper and more flexible but needs more coordination by the architect.

Drawings and visualisation

Grundriss, Schnitt, Ansicht (plan, section, elevation)
The three basic drawings in architecture. The plan shows a storey from above, cut horizontally about one metre above the floor. The section shows the building cut vertically with all heights. The elevation shows a facade from outside.
Lageplan (site plan)
Shows the plot from above with boundaries, neighbouring buildings, the planned building and its distances. The planning application requires an official site plan from a surveyor.
Aufmaß (building survey)
Measuring an existing building. The result is as-built plans: floor plans, sections and elevations of the state before conversion. They are the basis of all planning in existing buildings.
LiDAR, laser scan and point cloud LiDAR
A laser scanner samples rooms with millions of measuring points. The result is a point cloud, a three-dimensional, dimensionally accurate image of the building. Drawings and 3D models can be derived from it, faster and more precisely than with a tape measure.
Rendering and visualisation
A rendering is a computer-generated, photorealistic image of a building or space that does not yet exist. It shows light, material and mood and helps with decisions before anything is built.
Building Information Modeling BIM
A way of working in which the building is planned as a three-dimensional model enriched with information. Everyone works on the same model; quantities, costs and clashes can be derived from it.
Moodboard and item list
A moodboard brings together materials, colours, furniture and mood images and shows how a space should feel. The item list then records every piece of furniture, light and material with its supplier.

Energy, services and safety

Gebäudeenergiegesetz (Building Energy Act) GEG
The law governing the energy demand of buildings. It sets how well new buildings and renovated components must be insulated and what requirements apply to heating systems.
KfW Efficiency House KfW
A funding standard of the KfW bank. The number shows how much energy a building needs compared with a reference building: an Efficiency House 55 needs only 55 per cent. The smaller the number, the better and the higher the funding.
Wärmepumpe (heat pump)
A heating system that draws heat from air, ground or groundwater and uses electricity to raise it to heating temperature. It works especially efficiently with underfloor heating and good insulation.
Photovoltaik (photovoltaics) PV
Solar modules, usually on the roof, that convert sunlight into electricity for your own use or to feed into the grid.
Technische Gebäudeausrüstung (building services) TGA
All technical systems in a building: heating, ventilation, plumbing, electrics, lifts and building automation. They are designed by specialist engineers whom the architect coordinates.
KNX (building automation) KNX
A manufacturer-independent standard through which a building’s lighting, heating, blinds and other technology are networked and centrally controlled, the basis of many smart-home systems.
Brandschutzkonzept (fire safety concept)
Describes how a building protects people in a fire: escape routes, fire compartments, materials, smoke extraction and extinguishing systems. For larger and special buildings such as restaurants, halls or offices it is prepared by a fire engineer.
Tragwerksplanung (structural engineering)
The structural engineer calculates how floors, walls, columns and foundations must be dimensioned for the building to be stable. Their structural verification is part of the planning application.

Existing buildings and fit-out

Bestandsschutz (grandfathered rights)
A lawfully erected building may remain as it is even if regulations have since changed. With major alterations or a change of use this protection may lapse in whole or in part.
Denkmalschutz (heritage protection)
If a building is listed, almost every change needs approval from the heritage authority, including inside. In return there are tax benefits and grants.
Energetische Sanierung (energy-efficient renovation)
Measures that reduce the energy demand of an existing building: insulating facade, roof and basement, new windows, new heating, ventilation with heat recovery.
Unterfangung (underpinning)
The foundations of an existing building are extended downwards in sections, for example to deepen a basement or to build deeper right next to it.
Gaube (dormer)
A roof structure with a vertical window. It brings light and headroom into the attic and increases the usable area.
Mieterausbau (tenant fit-out)
Fitting out leased premises to the tenant’s requirements, for example for a shop, office, practice or restaurant. The lease should state who pays for what and what must be reinstated on moving out.
Rohbau und Ausbau (shell and fit-out)
The shell is the load-bearing frame of a building: foundation, walls, floors and roof. The fit-out is everything after: windows, building services, screed, plaster, flooring, doors and built-in elements.